Industrial Equipment Quote Comparison Worksheet

Use this worksheet to compare two machinery suppliers after you have a shortlist. Enter costs on the same scope through the first accepted part, then record the items each supplier still needs to confirm.

Give both suppliers the same job

Also give both suppliers the same delivery point, shop utilities and target production date. Ask each to list departures from the brief in writing.

Price the work through the first accepted part

Quote A
Quote B

A lower machine price can cost more by the time it produces an accepted part. For example, ask both suppliers who pays for rigging, whether the quoted tooling covers your sample part, and what support is included during the acceptance run.

Use a decimal point and up to two decimal places. Enter 0 for an item already priced elsewhere or confirmed to have no separate cost. For a required item the supplier excludes, enter a buyer-side estimate or leave the amount blank until it is priced.

One-time costQuote AQuote B
Machine and included options
Tooling, accessories and one-time software
Freight, unloading and rigging
Site preparation and utilities
Installation, training and acceptance run
Taxes and other one-time costs on the same basis
Estimated total Pending Pending
Compare the estimates after both pricing columns are complete and the scope matches. Estimated cost difference

Resolve the differences before placing an order

  1. Confirm quote expiry, lead time, who unloads and what your shop must supply before installation.
  2. Agree on the sample part, inspection method and what happens if the machine misses the acceptance criteria.
  3. Compare warranty, parts and service access. Track annual software, maintenance and consumables separately over the same period.